Description: Replacement of approximately 1,600 feet of 8” water main on S. Normal Avenue and S. University Avenue from W. College Street to W. Grand Avenue. The existing water main has broken several times and is in poor condition.
Start Date: Spring 2024
Estimated Completion Date:
Location: S. Normal Avenue
Estimated Project Cost: $176,400
Funding Source: City of Carbondale Utility Fund Revenues, Water & Sewer User Fees
Contractor: TBD
Project Impact: Water customers in the area should expect minor service interruptions during construction. Specific details on service interruptions will be provided at a later date directly to the affected property owners.
Project Updates:
08/22/2023 - The project is being designed - expected start date early 2024.