North Wall Street Improvements

N. Wall Street Improvements

Description: The City of Carbondale will repave North Wall Street from East Main Street to East Fisher Street. This is a main road serving Northeast Carbondale, the Eurma Hayes Center, Thomas School, and Attucks Park. This road is in poor condition and replacing it will improve the infrastructure, provide better access to residents, and prevent greater costs to replace it in future years.

Start Date: Spring 2023               

Est. Completion Date: Spring 2023

Location: North Wall Street from E. Main to E. Fisher Street

Project Cost:   $300,000

Funding Source: 80% of the funding for this project comes from the Southern Illinois Metropolitan Planning Organization. The City will fund the remaining 20%.  

Contractor: TBD 

Project Updates

2/16/23 - This project will be on the March IDOT bid letting.

8/31/22 - The City received environmental approvals from IDOT. The project will not be bid on until Spring 2023 due to it being late in the construction season.