Description: The City of Carbondale will repave North Wall Street from East Main Street to East Fisher Street. This main road serves Northeast Carbondale, the Eurma Hayes Center, Thomas School, and Attucks Park. This road is in poor condition, and replacing it will improve the infrastructure, provide better access to residents, and prevent greater costs to replace it in future years.
Start Date: Spring 2023
Est. Completion Date: Spring 2023
Location: North Wall Street from E. Main to E. Fisher Street
Project Cost: $382,667.75
Funding Source: 80% of the funding for this project comes from the Southern Illinois Metropolitan Planning Organization. The City will fund the remaining 20%.
Contractor: Samron Midwest Contracting
Project Updates
7/2023 - Work is complete.
3/14/23 - Bid awarded to Samron Midwest Contracting of Murphysboro, IL.
2/16/23 - This project will be on the March IDOT bid letting.
8/31/22 - The City received environmental approvals from IDOT. The project will not be bid on until Spring 2023 due to it being late in the construction season.